Contract 23389 REL 1: 200003801 EXP WALLA WALLA HATCHERY PRE-DESIGN - MCM
Project Number:
Title:
Walla Walla Hatchery Plan and Preliminary Design – Expense
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
23389 REL 1
Contract Title:
200003801 EXP WALLA WALLA HATCHERY PRE-DESIGN - MCM
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
Contract Objectives

The general objective of the contract is to develop predesign documents (30% design completion) for a spring chinook salmon hatchery and associated facilities on the South Fork of the Walla Walla River (SFWW) near Milton-Freewater, Oregon.  Further objectives are to: (1) obtain support associated with development of the facilities predesign, including managing the technical work group process that involves fishery co-managers and regulators; and (2) provide technical assistance in identifying environmental and construction permitting requirements.  

Project Background

This project involves building a hatchery to provide fish production needed to restore an extirpated spring Chinook population in the Walla Walla subbasin.  The project is part of the Northwest Power and Conservation Council’s (NPCC) F&W program, and is a component of Fish Accord between BPA and the Confederated Tribes of the Umatilla Indian Reservation (CTUIR).  

The SFWW project site is currently developed as a spring chinook adult holding and spawning facility operated by CTUIR.  Design and construction of the existing facility was funded by Bonneville Power Administration (BPA), and the facility began operation in 1996.  Existing infrastructure at the site includes a river water intake, water supply piping, holding raceways, spawning building, ozone water treatment building, staff housing, effluent pond, and effluent discharge line.  The water supply and treatment infrastructure were sized to accommodate the eventual full-scale hatchery facility addition.

New facilities to be developed include a building for egg incubation and early fish rearing, and approximately 20 outdoor raceways for full-term fish rearing through the smolt stage.  Connections of the facility additions to the existing water supply and effluent discharge systems will also be required.
Account Type(s):
Expense
Contract Start Date:
05/01/2010
Contract End Date:
09/30/2011
Current Contract Value:
$224,121
Expenditures:
$224,121

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Time and Materials
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration No Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jay Marcotte Bonneville Power Administration Yes COR jgmarcotte@bpa.gov (503) 230-3943
Mara McMillen McMillen Jacobs Associates Yes Contract Manager mara.mcmillen@mcmillen-llc.com (208) 342-4214
Mort McMillen McMillen Jacobs Associates No Supervisor mort.mcmillen@mcmillen-llc.com (208) 342-4214
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Brian Zimmerman Umatilla Confederated Tribes (CTUIR) No Interested Party brianzimmerman@ctuir.org (541) 429-7286


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Well managed project B: 119. Project management for all project activities 06/10/2011 06/10/2011
facility water sources, amounts and treatment needs determined C: 174. Task A1 Determine Water Supply & Water Quality Needs of the Facilities 03/04/2011 02/04/2011
recommendations to integrate fixes into facility design D: 122. Task A2 Conduct Operational Review of Existing SFWW Facilities 01/21/2011 01/21/2011
Recommendations for fish loading system E: 122. Task A3 Conduct Operational Review Nursery Bridge Trapping/Holding Facility 01/21/2011 01/07/2011
site survey data collected F: 157. Task A4 Finalize site survey 01/21/2011 01/07/2011
complete bio-programming plan for hatchery G: 162. Task A5 Develop Detailed Bioprogramming and Water Budget 01/28/2011 01/07/2011
Decision matrix for incubation and early rearing technologies H: 162. Task A6 Conduct Technical Analysis of Alternative Incubation/Early Rearing 02/04/2011 02/15/2011
Preliminary drawings and specification outlines I: 175. Task A7 Develop 30% Design Document 06/01/2011 06/01/2011
30% cost estimates J: 175. Task A8 Develop Cost Estimates 06/01/2011 06/01/2011
EC strategy memo prepared K: 165. Task A9 Summarize Likely Environmental and Construction Permits 06/01/2011 06/01/2011
Estimate and schedule for final design L: 175. Task A10 Prepare an Estimate and Schedule for Final Design 06/01/2011 06/01/2011
Preliminary construction schedule M: 175. Task A11 Develop a Preliminary Construction Schedule 06/01/2011 06/01/2011
Final Basis of Design Report N: 141. Task A12 Prepare the Predesign Report 07/30/2011 07/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 2 instances of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 4 instances of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 06/01/2010
B 119 Project management for all project activities 06/01/2010
C 174 Task A1 Determine Water Supply & Water Quality Needs of the Facilities 06/01/2010
D 122 Task A2 Conduct Operational Review of Existing SFWW Facilities 06/01/2010
E 122 Task A3 Conduct Operational Review Nursery Bridge Trapping/Holding Facility 06/01/2010
F 157 Task A4 Finalize site survey 06/01/2010
G 162 Task A5 Develop Detailed Bioprogramming and Water Budget 06/01/2010
H 162 Task A6 Conduct Technical Analysis of Alternative Incubation/Early Rearing 06/01/2010
I 175 Task A7 Develop 30% Design Document 06/01/2010
J 175 Task A8 Develop Cost Estimates 06/01/2010
K 165 Task A9 Summarize Likely Environmental and Construction Permits 06/01/2010
L 175 Task A10 Prepare an Estimate and Schedule for Final Design 06/01/2010
M 175 Task A11 Develop a Preliminary Construction Schedule 06/01/2010
N 141 Task A12 Prepare the Predesign Report 06/01/2010
O 132 No report required - see WE "N" 06/01/2010